New LPG import terminal commissioned at Krishnapatnam
Petregaz has commissioned a new LPG import terminal at Krishnapatnam.
As per a communique, details of the facilities and applicable restrictions are as follows:
* Terminal: Petregaz Krishnapatnam Private Limited
* Capacity: 1.5 million metric tonnes
* Maximum LOA: 285 m
* Beam: 50 m
* Maximum draught: 15.00 m
* Displacement: 180,000 MT
* DWT: No restriction
* Tankages: 2 x 30410 CBM Refrigerated Tanks for Propane & Butane
* Pipeline: 16 inch pipeline 3 km length
* Manifold/Flange: 12 inch x 300 ANSI for both grades
* Average Discharge Rate: 600 MT per line per hour (total 2 lines)
Source: Exim News Service: Krishnapatnam, April 25